Request a DemoLog In(844) 692-0626
    • Americas
    • América Latina (Español)
    • Canada (English)
    • Canada (Français)
    • United States (English)
Request a DemoLog In
cta-construction-image

Take Your Knowledge to the Next Level

Unlock your career potential with our free educational courses on Health & Safety, Data in Construction, and more.

Learn More

—  5 min read

Construction Purchase Orders 101: A Contractor’s Guide to POs

By 

Last Updated Jun 16, 2024

By

Last Updated Jun 16, 2024

2 contractors wearing PPE at construction site surveying amount of concrete needed for concrete pour

The construction purchase order (PO) is a document that outlines the price and quantity of goods or services necessary to complete a project contract as agreed upon by two parties — the buyer and the seller. The buyer (usually an owner or general contractor) issues a PO to the seller (usually a general contractor or specialty contractor) to cover the cost of the project.

Construction purchase orders are key financial elements of an overall project contract. Keep reading to learn the main components included in a purchase order, an example scenario of those elements in use, and some differences between purchase orders, invoices, and contracts.

Table of contents

What information does a construction purchase order contain?

When drafting a PO, it’s important to remember to be explicit and detailed when filling out the following sections:

  • Description of deliverables
  • Number (or quantity) of deliverables
  • Agreed-upon cost
  • Terms of payment
  • Due dates
  • Method of delivery
  • Reference numbers

In order to illustrate the contents of a construction purchase order and how they are relevant to the completion of a project, let’s use a hypothetical scenario featuring construction professionals Jane and John.

Let’s say Jane is a project manager at a GC hired to build a warehouse while John is a concrete contractor who won the bid to pour the foundation of that warehouse.

Description of deliverables

Upon receiving the bid for the concrete pour, John and his team visit the site. They identify the tools, equipment, materials, and labor needed to complete the project. Once he relays that information to the GC, Jane’s team will draft a PO for the deliverables outlined by John and his team. 

Number of deliverables

As Jane’s team is drafting the PO, they have to be diligent with listing the quantities for each deliverable provided by John. This is important because a PO explicitly states the GC’s fiscal responsibility for the deliverables needed to complete the work expected of the specialty contractor. This document, therefore, protects both parties by ensuring that:

  • The GC receives the amount and quality of work requested
  • The SC gets paid for the items needed to complete the work requested

Get the latest U.S. retail prices and view historical trends for common building materials.

Material Price Tracker

Agreed-upon cost

As Jane’s team lays out the itemized list of deliverables requested by John’s team, the two parties will agree on a cost per item and possible discounts for certain quantities of those items. 

Terms of payment

The terms of payment for a construction purchase order are usually based on credit. The GC sends the PO to the SC to request a service on credit. This protects the GC in the event that payment is given before the completion of the project. 

The terms of payment can also be set in regard to a net payment term. It defines how many days after an invoice is submitted the buyer has to make the payment. In this scenario, we will say that Jane approves a PO with a net 30 term, which means John will be paid within 30 days of submitting an invoice for the completed work. 

Due dates

Now that the parties have agreed to the terms of payment, Jane's and John's teams will decide on due dates for the deliverables requested in the PO. These dates will inform the date of delivery of those deliverables.  

Method of delivery

One of John’s deliverables in the PO is an extra concrete mixer that has to be shipped from out of state. The delivery method for that mixer will typically be defined as one of two FOB (Free On Board) shipping terms: FOB Shipping Point (or FOB Origin) and FOB Destination. If “FOB Origin” is agreed upon, the GC will become responsible for any loss or damages incurred to the mixer as soon as it leaves the warehouse and is in transit to the job site. If “FOB Destination” is agreed upon, the SC will be responsible for any damage incurred to the mixer until it reaches the job site. 

Reference numbers

The reference number is one of the most important pieces of the construction purchase order — it helps track the document. Since a project can have hundreds of PO’s attached to it, they can commonly become lost or jumbled during a project’s lifetime. The only way to prove that a service or material was completed or delivered as requested is to be able to locate the respective PO by its reference number.

The difference between a construction purchase order & an invoice

There is one main difference between a construction purchase order and an invoice: A purchase order is submitted by the buyer, while an invoice is submitted by the seller. So in our example, a PO is submitted by the buyer, Jane the GC, to determine the cost of a contract before the work is completed.

In contrast, an invoice would be submitted by the seller (John the SC) after the work is completed to receive an agreed-upon payment.

A Contractor’s Guide to Construction Invoicing

The difference between a construction purchase order & a contract

While they're both legally binding documents, a purchase order is not a contract. A contract is a legally binding document that covers all products, agreed prices, and payment terms and conditions for the entirety of a construction project. A contract includes all necessary purchase orders (documents that outline the price and quantity of goods or services necessary to complete the project contract) and invoices. A purchase order is one document that outlines the price and quantity of goods or services necessary to complete the project.

Was this article helpful?

Thank you for your submission.

85%

15%

You voted that this article was . Was this a mistake? If so, change your vote here.

Scroll less, learn more about construction.

Subscribe to The Blueprint, Procore’s construction newsletter, to get content from industry experts delivered straight to your inbox.

Thank you!

You’re signed up to receive The Blueprint newsletter from Procore. You can unsubscribe at any time.

Categories:

Resource Management

Written by

Jonny Finity

27 articles

Jonny Finity creates and manages educational content at Procore. In past roles, he worked for residential developers in Virginia and a commercial general contractor in Bar Harbor, Maine. Jonny holds a BBA in Financial Economics from James Madison University. After college, he spent two and a half years as a Peace Corps Volunteer in Kenya. He lives in New Orleans.

View profile

Explore more helpful resources

article-image

The Construction Buyout Process Explained

Although every construction project is unique, all projects progress in several common phases, from predevelopment through to closeout. Each stage of a project builds on the ones before it. During...

article-image

How to Create a Construction Safety Training Program

In construction, a strong safety program doesn’t just establish compliance and protect workers—it demonstrates a company’s investment in its people, improves employee morale, drives productivity, and enhances a company’s reputation. ...

article-image

Mastering Construction Branding: Win Bids & Attract Talent

A construction company’s reputation and branding go hand in hand to help win bids, attract and retain talent in a tight labor market, and project a positive image to the...

article-image

Measuring Success and Leveraging Metrics in Construction Technology

The implementation of construction software is supposed to be an exciting phase of tech adoption, a time when planning, evaluating and collaborating begins to yield results. However, realizing the excitement...

Procore is committed to advancing the construction industry by improving the lives of people working in construction, driving technology innovation, and building a global community of groundbreakers. Our connected global construction platform unites all stakeholders on a project with unlimited access to support and a business model designed for the construction industry.

LinkedIn Icon
LinkedIn
Facebook icon
Facebook
Twitter icon
Twitter
Instagram Icon
Instagram
YouTube icon
YouTube

Call us at (844) 692-0626 to speak with a product expert.

Apple LogoApple App StoreGoogle Play logoGoogle Play

Downloads

Apple LogoApple App StoreGoogle Play logoGoogle Play
  • Privacy Notice
  • Terms of Service
  • Do Not Sell Personal Information

© 2024 Procore Technologies, Inc.